Complete NTM 99/18

Latitude 55° 57.617’ North (WGS-84 datum)
Longitude 004o 48.835’ West (WGS-84 datum)

 

Mariners are advised that contractors NG Builders Ltd will be undertaking repairs to the linkspan decking at Gourock Ferry Terminal, Firth of Clyde.

Weather permitting, works are scheduled to commence on 06 November 2018 and are expected to last for three weeks.

During the period of the works the linkspan will remain operational for foot passengers but should any RoPax ferry need to divert to Gourock during this time the linkspan can be made available for vehicular traffic subject to the current weight restrictions. Masters are required to make early contact with the Gourock Harbour Manager to confirm their need to divert to the location and provide sufficient time for the contractor’s equipment to be cleared from the linkspan.

The contractor’s supervisor will monitor VHF channels 12 and 16 and will liaise with the Gourock Harbour Manager and Masters of the Argyll ferries to ensure the risk of disrupting the scheduled ferry services is minimised.

Further details can be obtained using the contact details below.

David McHardie

Harbour Master

Caledonian Maritime Assets Limited
Municipal Buildings, Fore St.,
Port Glasgow
PA1 4 5EQ
Tel: 01475 749 920
email: info@cmassets.co.uk