NTM 91/21 Tarbert (Harris) Removal of Pier Temporary Draught Restriction
Latitude 57º 53.805’N | Longitude 006º 47.912’W |
WGS 84 Datum |
WGS 84 Datum |
With reference to NTM 85/21, mariners are advised that contractors have managed to progress works to remove three temporary piles, fendering and the supporting concrete foundation blocks from the linkspan berthing area of the new pier under construction at Tarbert Ferry Terminal Pier, East Loch Tarbert, Isle of Harris. The area is now clear of obstructions.
Hence, the temporary maximum draught restriction of 3.3m has been removed and NTM 89/21 is cancelled.
Further details can be obtained using the contact details below.
Issued on behalf of the Harbour Master
Caledonian Maritime Assets Limited
email: operations@cmassets.co.uk
Categories: Notice to Mariners
Tags: