Latitude 57º 53.807′ North (WGS-84 datum)
Longitude 006º 47.927′ West (WGS-84 datum)

 

Mariners are advised that contractors RJ MacLeod Ltd will soon be commencing reconstruction of Tarbert Ferry Terminal and inner harbour area, Isle of Harris. Works are scheduled to continue for approximately 18 months.

Preparatory works will begin on week commencing 21 October 2019 with the relocation of the pontoons from the inner harbour, bathymetric survey, reclamation works and dredging following thereafter.

During the reconstruction scheduled ferry services will continue operation however, pier access by other vessels will be restricted and only permitted by prior arrangement with the CalMac Ferries Ltd Port Manager in liaison with the works supervisor.

During any marine works the supervisor will ensure VHF Channels 12 and 16 are monitored and will liaise with the Port Manager and Master of the CalMac Ferry to ensure there is no disruption to scheduled ferry services.

As works progress additional information will be issued to mariners in subsequent NTM updates.

Further details can be obtained using the contact details below.