Cabinet Secretary for Transport, Infrastructure and Connectivity Michael Matheson said: “Ferguson Marine Engineering Ltd has advised us that the first vessel, the MV Glen Sannox, will now be delivered
-
The UK’s first liquefied natural gas (LNG) passenger ferry was launched today (Tuesday 21st November 2017) on the Clyde by First Minister Nicola Sturgeon. The 102-metre, roll-on/roll-off vehicle passe
-
A major logistical engineering operation took place on the Clyde today (Friday 14th July) when an 88-tonne liquefied natural gas (LNG) tank was delivered to Ferguson shipyard, marking a significant mi
-
MV GLEN SANNOX has been chosen as the name for Caledonian Maritime Assets Limited’s (CMAL) new dual fuel ferry.
-
Caledonian Maritime Assets Ltd (CMAL) has announced a shortlist of names for the first of its two 102 metre dual fuel ferries and is inviting the public to vote for their favourite name. The shortlist
-
view the presentation given to the Arran Ferry Committee
-
The new ships will be highly manoeuvrable, with Twist Flow Costa Bulb Flap Rudders, three 620 kW bow thrusters and a 480 kW stern thruster
-
Caledonian Maritime Assets Limited (CMAL) will host a series of public meetings to update communities on the design and build of the new dual fuel vessel for the Skye Triangle route and to discuss har
-
The construction of two dual fuel ferries is approaching a new project milestone as the first vessel, currently known as Hull 801, nears the 75 per cent steelwork fabrication stage, Caledonian Maritim
-
The tank has been designed by Wartsila, the main contractor for the ship’s propulsion package
-
Transport Scotland’s ferries unit visits Ferguson Marine Engineering in Port Glasgow and witnesses work on the two state-of-the-art vessels
-
Presentation delivered by Alistair Chan, our Civil Engineer at the Lochaline Stakeholder Engagement/Public meeting, 7:00pm on 26th January at the Lochaline Village Hall Click below to download a PDF c
-
The steel cutting ceremony took place at FMEL shipyard in Port Glasgow, where the ships are being built.
-
Presentation by Ruairidh Campbell of CMAL delivered to Colintraive and Glendaruel Community Council on Monday, 15th February, 2016 at 7.30 pm held at Colintraive Village Hall. Click here to download t
-
Two 100-metre vessels to be built on the Clyde. The Minister for Transport and Islands has marked the formal start of construction of two new 100-metre ferries for the Clyde and Hebrides network at Fe
-
Steel was cut today for Caledonian Maritime Assets Ltd’s two new ferries being built by Ferguson Marine Engineering Ltd (FMEL), marking the start of construction on the £97 million vessels. The steel-
-
CMAL met with Community Councillors in North Uist this month to deliver a presentation on the two new 100 metre dual fuel ferries. A copy of the presentation is available here (Powerpoint 3mb). The f
-
The Scottish Transport Minister announced the build and design two new ferries for use on the Clyde and Hebrides Ferry Services.
-
How long will the works take and are you confident that you will meet this revised timetable? What contingency have you built in? The works are programmed to last a total of 24 weeks which will includ
-
Ferguson named preferred tenderer for new £97m vessels contract First Minister Nicola Sturgeon has confirmed Ferguson Marine Engineering Limited (FMEL) as the preferred tenderer for the contract to bu