The contract to transform the ferry terminal in Brodick has been awarded to George Leslie Limited by Caledonian Maritime Assets Limited (CMAL). The contract is worth over £22.2 million and is part of
-
Caledonian Maritime Assets Ltd (CMAL) has appointed a contractor to undertake essential groundworks at Brodick Ferry Terminal, in advance of the main redevelopment project. These works are due to star
-
Below are questions/issues raised during public communication meetings in relation to refurbishment works at Wemyss Bay on Tuesday 15th September 2015. Wemyss Bay Project Q and A September 15, Click t
-
How long will the works take and are you confident that you will meet this revised timetable? What contingency have you built in? The works are programmed to last a total of 24 weeks which will includ
-
Monday 11th May 2015 – 19:00 Bute Community Council – Public Meeting – Bute Ferry Services Attended by CMAL, Transport Scotland and CalMac. CMAL provided project update:- Reminder of works – re-fender
-
Tender returns have been received from a number of shipyards for the Detailed Design and Construction of two LNG fuelled ROPAX ferries of approximately 100m in length. These ferries are being designe
-
The Q&As and presentation from meetings that took place on 24th Feb at Inverkip and 26th Feb on Isle of Bute are available to download below. Wemyss Bay Project Specific QandA, Click to download (
-
Inverkip Caledonian Maritime Assets Ltd (CMAL) will host a public meeting on Tuesday 24th February, 18:30 at The Chartroom, Inverkip Marina. CMAL will present information regarding the postponement of
-
Caledonian Maritime Assets Ltd (CMAL) has announced that for technical reasons, the planned closure of the pier at Wemyss Bay Ferry Terminal will be postponed from March 2015 until later in the year,
-
Presentation and Q & A Please find below both PPT presentation and Q & A following our recent Public Meetings regarding Wemyss Bay Ferry Terminal refurbishment works • Public Meeting Presentat
-
Wemyss Bay harbour will undergo significant investment to secure a safe, efficient and reliable service to Rothesay. As part of this investment, the Wemyss Bay ferry terminal will be closed for 16 we
-
Brodick Harbour Redevelopment Group is pleased to announce that funds have been secured to move forward with the redevelopment works at Brodick Ferry Terminal as a single phased project, due for compl
-
CMAL are planning to hold a public/ stakeholder meeting in relation to the Lochranza Seawall Replacement Project at Lochranza and Catacol Village Hall on Monday 10th March 2014, from 18-00 to 20-00 ho
-
The detailed design work on the Brodick Ferry terminal redevelopment project is continuing. Liaison with stakeholders on technical issues is being undertaken as the design proceeds. The ground investi
-
Presentation showing the improvements due for the Ullapool Pier. Ullapool Pier Improvements November 2013 (PDF, 43.2Mb) Includes information on: • Plans/technical drawings/video • Passenger Access Sys
-
The world’s first hybrid ferry sailed its maiden voyage this week (25th November) on its route between Sconser and Rasaay. The MV HALLAIG is the first passenger and vehicle roll-on, roll-off ferries i
-
Caledonian Maritime Assets Ltd can confirm that an incident occurred on Wednesday 30th October at the slipway at Tobermory Harbour, during planned upgrade works. While a contracted lorry was unloading
-
To ensure passenger safety, CMAL needs to undertake urgent remedial work on the Gourock Linkspan to install two permanent working platforms at the front and rear and to remove, refurbish and replace b
-
Following completion of the tendering process where seven contractors took part. We would like to advise you that the successful tenderer for the above works is McLaughlin Harvey Ltd. Please click her
-
CALEDONIAN MARITIME ASSETS LTD & THE HIGHLAND COUNCIL Comhairle na Gàidhealtachd TEC SERVICES Hybrid Ferry and Port Infrastructure Public Meeting All Welcome Caledonian Maritime Assets Ltd and The