Caledonian Maritime Assets Ltd (CMAL) have now awarded the contract to redevelop the Brodick Ferry Terminal, and would like to update local individuals, groups and businesses on the project, as well a
-
Mariners are advised that weather permitting, repair works will commence at Oban Ferry Terminal Linkspan no. 1 berth at 0700hrs Monday 16th November 2015 and are programmed to be completed by 0700hrs
-
Caledonian Maritime Assets Limited (CMAL) has completed the £1 million comprehensive upgrade of the Grade A listed building that forms the Wemyss Bay Ferry Terminal. The existing timber walkway, ticke
-
The contract to transform the ferry terminal in Brodick has been awarded to George Leslie Limited by Caledonian Maritime Assets Limited (CMAL). The contract is worth over £22.2 million and is part of
-
Caledonian Maritime Assets Ltd (CMAL) has appointed a contractor to undertake essential groundworks at Brodick Ferry Terminal, in advance of the main redevelopment project. These works are due to star
-
With reference to NTM 51/15 mariners are advised that repairs to the mooring gear of the navigation buoy at Braigh Mor, East Loch Tarbert, Isle of Harris are complete and the buoy has been returned to
-
With reference to NTM 43/15 mariners are advised the outer Port Ellen Shoal Buoy has been returned to station. The aforementioned NTM is now cancelled. Please click here to download a printable PDF of
-
Mariners are advised that Caledonian Maritime Assets Ltd have established a new lit starboard hand buoy to mark the edge of the shoal within the inner harbour approaches at Port Ellen, Isle of Islay.
-
Mariners are advised that a routine maintenance inspection has identified a critical defect on the mooring gear of the navigation buoy at Braigh Mor, East Loch Tarbert, Isle of Harris. This has requir
-
Mariners are advised contractor Lanarkshire Welding Company Limited is undertaking maintenance and repair works to Gourock Ferry Terminal linkspan. Weather permitting, works are programmed to commence
-
Below are questions/issues raised during public communication meetings in relation to refurbishment works at Wemyss Bay on Tuesday 15th September 2015. Wemyss Bay Project Q and A September 15, Click t
-
How long will the works take and are you confident that you will meet this revised timetable? What contingency have you built in? The works are programmed to last a total of 24 weeks which will includ
-
Mariners are advised contractor George Leslie Ltd is installing timber rubbing strips to the front of the berthing steps platforms located adjacent to Gourock Ferry Terminal linkspan and painting work
-
Mariners are advised that the Craggy Island Triathlon event will be taking place on the Isle of Kerrera, Argyll during 5th and 6th September 2015. Approximately 225 competitors will participate in the
-
Mariners are advised that unreported damage has been caused to fendering on Mingary Pier, Kilchoan, Ardnamurchan. The extent of the damage requires CMAL to close the pier to all vessels until further
-
With reference to NTM 45/15 mariners are advised that due to unfavourable weather the start of repairs to the linkspan berthing area fendering at Wemyss Bay Ferry Terminal has been delayed until furth
-
Mariners are advised that contractors NG Builders Ltd will be undertaking repairs to the linkspan berthing area fendering at Wemyss Bay Ferry Terminal. Works will commence during the evening of Thursd
-
Mariners are advised that works to inspect the linkspan at Gourock Ferry Terminal will be undertaken on Wednesday 19th August 2015. It is anticipated the inspection will be completed within one day. C
-
Mariners are advised that the starboard hand navigation mark indicating the edge of the shoal area to the south of Port Ellen Ferry Terminal, Islay is reported to be off station approximately 25m sout
-
Mariners are advised that on Thursday 6th August 2015, GSS (Plant) Ltd is undertaking a dive project to inspect Portavadie Ferry Slipway, Loch Fyne. To ensure there is no disruption to scheduled ferry