Complete

Latitude 57º 53.807′ North (WGS-84 datum)
Longitude 006º 47.927′ West (WGS-84 datum)

 

 

Mariners are advised that on 21 October 2019, contractors RJ MacLeod Ltd commenced reconstruction of Tarbert Ferry Terminal and inner harbour area, Isle of Harris. Works are scheduled to continue for approximately 18 months.

During the reconstruction scheduled ferry services will continue operation however, pier access by other vessels will be restricted and only permitted by prior arrangement with the CalMac Ferries Ltd Port Manager in liaison with the works supervisor.

During any marine works the supervisor will ensure VHF Channels 12 and 16 are monitored and will liaise with the Port Manager and Master of the CalMac Ferry to ensure there is no disruption to scheduled ferry services.

As works progress additional information will be issued to mariners in subsequent NTM updates.

Further details can be obtained by using the contact details below

David McHardie

Harbour Master
Caledonian Maritime Assets Limited
Municipal Buildings,
Fore St. Port Glasgow
PA1 4 5EQ

Tel: 01475 749 920


Categories: Fios gu Maraichean
Tags: