Wemyss Bay Ferry Terminal
Wemyss Bay reopened – 24 March 2016
Services to Rothesay reopened for travel again on Friday 25th March 2016 in time for the busy Easter holiday traffic.
The pier was closed for six months for essential repairs with services diverted to Gourock. The worked we carried out included the replacement of timber fenders, reconstruction of the pier end and refurbishment of the linkspan. The harbour has also been dredged.
The scope of the work is shown in the reports below.
Progress Update – 8th February 2016
Wemyss Bay Pier Refurbishment-Progress Update No 4 (PDF, 897Kb)
Progress Update – 8th January 2016
Wemyss Bay Pier Refurbishment-Progress Update No 3 (PDF, 831Kb)
Progress Update – 2nd December 2015
Wemyss Bay Pier Refurbishment-Progress Update No 2 (PDF, 938Kb)
For ‘Progress Update – 29th October 2015, please click here (PDF, 820kb)
November 2015
On 5 November we announced that we had completed the £1 million comprehensive upgrade of the Grade A listed building that forms the Wemyss Bay Ferry Terminal. The existing timber walkway, ticket office and store facilities have all been refurbished as part of a £6 million investment.
The building is over 100 years old and is a prominent wrought iron and timber clad structure with a slate and glass roof. All defective timbers were replaced on the external and internal walls, including the concealed structural timbers, which form each of the 44 timber bays. The main structural frame of the walkway is constructed from a number of wrought iron trusses that are supported off concealed wrought iron columns. All of the concealed and exposed wrought iron structure has been repaired, cleaned and redecorated, including the columns, trusses and wrought iron lateral restraints. All downpipes and guttering systems have been replaced and the glazed roof lights were cleaned.
Additional work to the exterior of the terminal started on 1st October 2015 for a period of around 24 weeks and includes removal and subsequent reinstatement of the vehicle linkspan, demolition and re-construction of the existing 1970s load restricted pier roundhead, renewal of pier fendering, installation of corrosion protection to the pier and dredging to the west and south of the pier. The nature of this work means the ferry terminal will be closed for the duration and is expected to re-open on completion of all work before Easter 2016.
Progress Update – 29th October 2015
Wemyss Bay Pier Refurbishment- Progress Update No 1- 29th October 2015 (PDF, 820 Kb)
Drop in Sessions
Caledonian Maritime Assets Ltd will hold drop in sessions for ongoing communications regarding the redevelopment of Wemyss Bay Ferry Terminal. These sessions will allow members of the public to meet project lead, Senior Civil Engineer, Brian Sydney and others from the project team. The team will be on hand to answer questions about the project and its progress. Times and dates for both Rothesay and Wemyss Bay can be found below:
Rothesay- Green Tree Room, Moat Community Centre, 18.00 to 20.30
2015: 15/10, 29/10, 12/11, 26/11, 10/12
2016: 7/1, 21/1, 4/2, 18/2, 3/3
Wemyss Bay- Ferry Terminal Waiting Room, 09.30 to 12.00
2015: 9/10, 22/10, 6/11, 20/11, 4/12, 18/12
2016: 15/1, 29/1, 12/2, 26/2, 11/3
Project Update on the internal works – May 2015
Major external and internal refurbishment of walkway, roof area, glazing and ticket office.
Progress to date:
- Joinery and steel works ongoing to North and South elevations
- Joinery finishing works commenced on both elevations
- Preparation and decoration to concealed steel work and internal timbers ongoing
- Slating, lead and gutter works ongoing
- Flat roof repairs above ticket office
- Glass renewals to roof and cleaning to glazing
- External cladding to Pierhead / Ticket Office